3 plots, North Coker

We have been commissioned by Cherwyn Developments in collaboration with Abbey Manor Group to undertake the groundworks for 3 plots at North Coker. We are currently in month 6 where we have pulled away from the site to allow the structures to be built.

So far on site we have undertaken:

  • Erect all heras fencing around site and flailing to the hedgerow.
  • Excavate the site to reduce all the levels for the plots and the road
  • Move excess subsoil and topsoil away from site using our own tippers
  • Delivering our own crushed concrete into site
  • Make temporary road in to allow machines and lorries to enter the site
  • Excavate pits for electric boxes
  • Setting out for road and plots
  • Foundations to all plots and garages
  • Install all drainage in the ground
  • Block and beam
  • Excavate trenches for services
  • Install attenuation tank in excavated trench